On U.S. 281, end in sight for roadway rehab

LOS INDIOS — The $3.9 million rehabilitation and widening of U.S. 281 from FM 509 west for more than a mile and a half is rapidly nearing completion.

The project is the latest section of work on one of the Valley’s oldest east-west corridors, and widens the narrow two-lane road also known as Military Highway to four lanes.

“In addition, they’re also constructing driveways, they’re pouring the concrete driveways as well as the asphalt driveways throughout the project length,” TxDOT engineer Candido Bocanegro told members of the Harlingen-San Benito Metropolitan Planning Organization this past week.

At the job site just west of Los Indios, three of the four asphalt lanes are already in place, and TxDOT lists the project as being 72 percent complete.

But crew members with Foremost Paving Inc. of Elsa said yesterday they are rapidly accelerating their work on the 1.65-mile project, which began in January.

Workers paved the fourth and final lane of the roadway on Thursday. Then, they said, they planned to repave and finish the intersection of U.S. 281 and FM 509, a key crossing to the Free Trade International Bridge at Los Indios.

By this week, they said they would be striping the roadway and it should be fully open to traffic soon after that part of the job is completed.

Most of the private driveways have been laid with asphalt. Some are constructed of concrete.

Some 6,283 square yards of asphalt has been laid for 34 driveways affected by the project, said TxDOT spokesman Octavio Saenz. The number of concrete driveways was less, about 14, with approximately 1,200 square yards of material used.

The newly refurbished and widened highway extends from FM 509 west to .05 miles west of FM 1479.

The border highway connects Brownsville to I-69C in McAllen.

TxDOT Projects Update

FM 106 roadway reconstruction

Location: From FM 1847 to FM 510

Cost: $15.6 million

Project Length: 11.4 miles

Contractor: Texas SAI Inc.

Work started: November 2015

Completion date: December 2017

Work finished: 80 percent

The project consists of a major overhaul of the roadway and includes several wildlife underpasses and adjacent fencing.

BSIF at Los Indios

Location: Los Indios Free Trade International Bridge

Cost: $6.9 million

Project Length: .001 miles

Contractor: Foremost Paving Inc.

Work started: February 2015

Completion date: March 2018

Work finished: 78 percent

The new border safety inspection facility will inspect trucks from Mexico entering the United States. Work on the facility has been suspended since September while TxDOT awaits a land donation from Cameron County.

U.S. 281 roadway rehabilitation and widening

Location: From FM 509 to .05 miles west of FM 1479

Cost: $3.9 million

Project Length: 1.65 miles

Contractor: Foremost Paving Inc.

Work started: February 2017

Work finished: 72 percent

Bridge rehabilitation Rio Hondo lift bridge

Location: Rio Hondo

Cost: $12.4 million

Project length: 0.117 miles

Contractor: PCL Civil Contractors Inc.

Work started: Summer 2016

Completion date: February 2018

Work finished: 97 percent

The project consists of a complete overhaul of the mechanical lift bridge over the Arroyo Colorado. Traffic should begin crossing in late June.

State Highway 107

Location: Combes

Cost: $3.7 million

Project length: 0.465 miles

Contractor: Foremost Paving Inc.

Work started: August 2017

Completion date: October 2018

Work finished: 30 percent