TxDOT kicks off freeway project to add miles of new LED lighting

HARLINGEN — Highway engineers are ready to light it up.

TxDOT has begun a new illumination rehabilitation project to add LED lighting at various locations on interstates in the Lower Rio Grande Valley.

“The project has already begun,” said TxDOT spokesman Octavio Saenz. “It is an 18-month project in which we will be installing LED lights, and will begin almost simultaneously in both Edinburg and Brownsville.”

In Edinburg, the first section is between the intersection of I-69C and Montechristo Heights Road to I-69C and FM 495, Saenz said.

“In Brownsville the limit of the first section is between the intersection of I-69E and SH 100 to I-69E and University Boulevard,” he added.

Cost of the new and brighter LED lighting is $3.1 million and will take about a year to complete as workers start at both ends of the project and work inward.

Other locations which are scheduled to receive the LED lights are along I-2 and I-69E, and I-2/U.S. Expressway 83 from Mile 3 East to FM 800 (Bass Boulevard).

Also on the board are new lights along I-69E/U.S. 77-Expressway 83 from Whalen Road to Sherer Road in San Benito.

Work on the project by contractor Traf-Tex Inc. began in January.

PROJECTS

U.S. 281 Rehabilitation and Widening

Location: From .05 miles west of FM 1479 to 0.24 miles east of FM 506

Cost: $7.7 million

Project Length: 3.86 miles

Contractor: ASAGO LLC

Work started: June 2015

Completion date: February 2017

Work finished: 86 percent complete

The project on the highway along the Rio Grande consists of rehabbing the roadway and widening the existing road.

FM 106 roadway reconstruction

Location: From FM 1847 to FM 510

Cost: $15.6 million

Project Length: 11.4 miles

Contractor: Texas SAI Inc.

Work started: November 2015

Completion date: December 2017

Work finished: 47 percent complete

The project consists of a major overhaul of the roadway and includes several wildlife underpasses and adjacent fencing.

BSIF at Los Indios

Location: Los Indios Free Trade International Bridge

Cost: $6.9 million

Project Length: .001 miles

Contractor: Foremost Paving Inc.

Work started: February 2015

Completion date: June 2016

Work finished: 78 percent

The new border safety inspection facility will inspect trucks from Mexico entering the United States. Work on the facility has been suspended since September while TxDOT awaits a land donation from Cameron County.

U.S. 281 roadway rehabilitation and widening

Location: From .09 miles east of Hidalgo/Cameron county line to 0.24 miles east of FM 506

Cost: $5.2 million

Project Length: 2.789 miles

Contractor: Foremost Paving Inc.

Work started: February 2015

Completion date: February 2017

Work finished: 99 percent

This is the western end of the rehab and widening of border highway U.S. 281.

1 and 2 county road off-system bridge replacements

Location: Kornegay Road just south of FM 1561 and Mile Line 20 Road 0.5 miles east of Nelson Road

Cost: $1.4 million

Project length: Varies

Contractor: Valley Infrastructure

Work started: February 2016

Completion date: December 2016

Work finished: 90 percent

The two projects will replace aging bridges and their approaches.

Bridge rehabilitation Rio Hondo lift bridge

Location: Rio Hondo

Cost: $12.4 million

Project length: 0.117 miles

Contractor: PCL Civil Contractors Inc.

Work started: Summer 2016

Completion date: December 2017

Work finished: 42 percent

The project consists of a complete overhaul of the mechanical lift bridge over the Arroyo Colorado.

I-69E and I-2 interchange landscape improvements

Location: I-69E and I-2

Cost: $293,349

Project length: 0.1 miles

Contractor: Southern Landscapes

Work started: N/A

Completion date: N/A

Work finished: 0 percent